Undergrounding Upgrades To The Property
Hey guys,
we have a 4-plex in San Diego that we bought several months ago that was built in 1950. According to inspector's report, we needed electrical upgrades. One of the electricians told us city is under a project to underground all the electrical lines, and if we do not do upgrades the way city EXPECTS us, once our neighborhood is due for undergounding, we will have to REDO the whole thing again (like changing the location of the MAIN electrical panel from where it is now). Can they FORCE these upgrades to the owners? I am talking about a 15000-20000$ that will be required... It is not cheap... What we wanted to do is the very minimum, but to make sure our tenants are safe: just replace fuses in each unit with BREAKERS and leave it in the closets as we "grandfathered" them in and replace the main panel fuse with a breaker. But according to the advise of an electrician based on the city undergrounding requirements, we will have to RELOCATE the fuses from closets to the OUTSIDE of the building AND RELOCATE the main panel from where it is now to an opposite direction (closer to the main street). Can the city ENFORCE us to do this? Similar Tutorials
How to Lay Sod - The Right Way!
- Make sure the green side faces up! And, there are a few more steps if you want to ensure a nice looking lawn. Prepa ...
The Difference Between Volts, Amps, and Watts
- This article explains the difference between Volts, Amps, and Watts in an easy-to-understand non-scientific way. T ...
Water is Leaking from the Toilet – What do I do? (How to replace the wax seal for a toilet.)
- If there is water leaking from the toilet, you need to make sure that you know from where the water is leaking. Che ... Similar Topics From Forums
We recently purchased an apartment complex built in 1950. Inspector's report advised us to upgrade the main electrical panel (fuse box) on the outside of the building. He also advised us to relocate fuse boxes in closets stating it is unsafe and a fire hazard.
We met with several electricians to get a quote. It's so confusing because everybody says different things... FUSE BOXES IN THE CLOSET: One electrician advised us to flip the panel into the bathroom(closet is adjacent to bathroom) and install a breaker instead of a fuse box, another electrician claimed it's not up to code to have breakers in the bathroom. MAIN PANEL OUTSIDE THE BUILDING: One electrician advised us to upgrade the amperage (currently 30 amps), the other claimed it's an unnecessary change that drives the cost up since we do not have any appliances that require high amperage: no washers or dryers. So confusing. I want the property to be SAFE for our tenants, but cost-efficient for us. Any thoughts? thank you.
My existing service entrance consists of an external Meter can mounted on the outside of the garage wall directly behind a SD Main Breaker Panel (MBP) with a 150 amp main breaker. In order to support upgrades, I am installing a second MBP (200 amp) inside the garage in the wall cavity right next to the existing panel.
Local code requires that the upgraded Meter can be purchased from the City Utility. I have already confirmed with the local inspector that either 4/0 Al or 2/0 Cu SE cable are acceptable for both the existing and new MBP. My question is what is the code requirement for getting the 3 SE cables run from the dual lugs to the new panel? Can those conductors run into the same wall cavity where the existing panel is installed? If so, I'm certain they can't go through the same conduit nipple that connects the back of the meter can to the existing MBP. Can they route in behind/above/below the existing panel and through a hole in the wall stud to gain access to the adjacent stud bay to get to the new panel? If not, do they need to be routed out of the meter can on the external wall in conduit over to the next stud bay and then enter the wall there to gain access to the new panel? If external conduit is required I would expect it must be metallic as opposed to PVC. Best Regards, Ted
I am replacing a feed through breaker panel the bus bar and breaker was inverted but the main breaker is up and down with on being down and I also noticed that the plastic in the back that holds the bus bar is cracked.
I bought a newer model from the same manufacture that has a much better design and a better main breaker. But unlike the one I already have when you invert it the breaker slots don't line up and cover does not fit properly. I was thinking about just cutting out the center where the breaker slots are. I measured and if I cut it just right all I have to do is turn it over and it will line up just have to bolt or weld it in place. Would this be legal I also thought about putting the panel the way it came and feeding the bus bar hot and keeping the panel under the 6 throw rule. Or would that not work because I am using feed through. There will be 4 double pole breakers and the one main that feeds a sub panel. I really hate the cheap design of this panel. I plan to replace it with this.
I'm having quite the time finding an electrician who will quote this. Just about all of them say that what I need is to upgrade my main panel but I want to install a new main panel that is a part of the meter base outside and make my current 100A panel a sub. Maybe you people can tell me why nobody seems to want to do this. Here are a few shots of the existing meter (note what is apparently a 60A base here)
and a shot of the conduit headed underground. Like most homes built during this era, the conduit makes a right turn underground to enter through the cinderblock, ending up coming into the back of the main panel. This conduit encloses a 4 wire feed. edit: no, actually it is only a 3 wire feed which is a problem if I want to convert the original main panel a sub. Here's the existing panel. It's a 60's era Square-D split panel with a 30 amp sub panel for the finished basement. Those are low voltage wires to circuit taps for my home energy monitoring system btw. The reason I don't want to upgrade this panel are as follows: We won't be expanding the electrical west of this panel any more. All planned expansion (240v car charger in Garage, planned 3 season room with grid tie Solar on the roof) will be to the east. Upgrading the panel will require major surgery to the walls. Due to the way the original basement is engineered there, the walls have an intricate stud pattern behind the existing panel. I'd pretty much have to rip out a 4' section and redo it to make the access large enough to handle a 200A panel. Adding additional circuits to an upgraded panel will require an act of God due to the finished basement construction. There are no raceways for additional circuits. Based on this, my thoughts were to create a new 200A main panel outside based on something like the GE model TSM420CSCUP loadcenter. Here's a shot of this panel: This particular panel has room for three 2-pole breakers in addition to the 200A mains. I'd add a 100A 2-pole breaker for the existing panel, with the other two reserved for the garage/solar expansions. The issue with the contractors who have quoted the job appears to be the conduit going to the existing panel. I'm not sure what's wrong with it but it is apparently not compliant with current code. Obviously the bonding needs to change, new grounding electrodes need to be driven, and a water pipe ground needs to be established to the new main panel, but what else is required? I'd like to throughly research all the code considerations here so I can approach a contractor from a more knowledgable perspective then determine the best way to perform this upgrade. Due to POCO coordination and the need to cut household power for the duration of the job, I have no desire to DIY this one... So what exactly is wrong with the conduit running from the existing meter base to the existing load center? Why is everybody telling me that I can't do essentially what I've described above? What are the relevant code sections that will apply to this job? Should I be chatting with my AHJ about local considerations now or should I wait until I have the code requirements down pat (assuming the latter here)?
Hi, we drove past a triplex we are considering for purchase tonight. When we got out of the car to have a look around a bit, one of the tenants saw us and came out. He was telling us what he knew of the house and said the fuse box is on the outside of the house. This is a concern for us, because a) it is fuses and not breakers, which is preferable and b) we live in MN, which has extreme weather of all type. I have never heard of an outside fuse box before. Is it common? Will it pass an FHA inspection if we do decide to buy it? How difficult is it to relocate the panel to inside the house? Will it need to be moved? Thanks in advance for any advice.
Garage running Underground feeder 4/4/4 AL from main panel off dual 80 amp breaker.
Yesterday I found half the garage panel was inoperative. Tested lugs, one of the feeders is 120V, the other is at 80-90V. Swapped the feeders at the 80 amp main to ensure it wasn't the breaker. Same results. Tested at the 80 amp breaker at main panel, both legs 120V. When I remove the 80-90V feeder off the 80 amp main panel breaker and test it at the garage it drops from 80-90 to 0. No breakers trip. Is this one feeder line broken underground or split open and grounded to earth?
Hello,
I am redoing my electrical system from the weatherhead to the breaker box so I'm sure I'll be asking quite a few questions in the relatively near future. My city uses the 2008 NEC with virtually no amendments (none pertaining to what I'm doing). I've got a copy of the NEC... wow, what a document, HA! I've got the permit already and have been in contact with the inspector already. He says my best bet is to use 2 grounding rods (so he doesn't have to measure resistance in the soil etc if I only have one). What size (diameter) solid copper rods are used? What length? When they are placed 6' apart, is that: no more than 6, no less than 6, or exactly 6'? Thank you all for your help!
In a large bunkhouse we need to add a second range, water heater, and kitchen outlets. The existing panel is 125 AMP (with breaker), and don't want to redo entire panel. A consultant said to install a 200 AMP drop, with a panel to handle the additional load. Would you then feed each of the panels from that drop as main panels, or use a new 200 AMP panel as the main, and the 125 as a sub-panel from that? I assume in either instance, the grounding would be done as a 200 AMP service. Just realized if each was a main panel, the new one couldn't exceed 75 Amps, or total would be over 200. Any other ideas appreciated.
Had a Home Inspection (don't have the report yet.) The house was built in 1983. One thing the inspector said was a grounding wire should be put in from the panel in the garage to the outside box.
He also said I should have a new panel put in ($ 1,500-1,700). That's a lot of money especially when you're just buying a house. It sort of concerns me, but he didn't sound like it was urgent. I can't believe I'd have to replace circuit breakers. I'll get 3 estimates when I do this. Is this a normal problem for houses this age? I always think of my dad's 60 yr old house and he never once had a repairman. I think his electrical was ancient.
Hello, we recently purchased an above ground pool and had it installed. The city building inspector came out to inspect the electrical and said we would need a bonding grid around the pool and bonding plate in the trench. When I questioned how to do this, his response was to contact the pool manufacturer. I have done this and the manufacturer tells me that since my pool is aluminum wall and the rest of it is resin, I do not need the grid and plate, but will need to insert a bonding screw to the skimmer and drop a copper wire from the screw into the ground. I asked for a schematic on how to do this, but they could not help. I am also concerned that they told me something different then the building inspector did. Can anyone help me with this please? Right now I regret getting this pool, hoping someone can walk me off the ledge. Thank you so much for you time.
|