Installing Sconce Between Electrical Panels
I am putting a theater area in my basement, but my electrical panels are also in the same room. To keep the room symmetrical, it would look best to install the new panel two stud bays over and put the sconce in between - then it would match with the sconce on the other side. I can't put the sconce on the other side further back because of a doorway. I plan to paint the panels the same color as the walls so they blend a little better.
Anyhow, I attached a picture of the proposed layout. The sconce sticks about 5 inches out from the wall. Will the inspector approve such a setup? I should still be able to access the panels without an issue, but don't want to do something against code, or stupid in some way. Thanks! Similar Tutorials
How to Lay Sod - The Right Way!
- Make sure the green side faces up! And, there are a few more steps if you want to ensure a nice looking lawn. Prepa ...
The Difference Between Volts, Amps, and Watts
- This article explains the difference between Volts, Amps, and Watts in an easy-to-understand non-scientific way. T ...
Water is Leaking from the Toilet – What do I do? (How to replace the wax seal for a toilet.)
- If there is water leaking from the toilet, you need to make sure that you know from where the water is leaking. Che ... Similar Topics From Forums
I am having my inground pool renovated. The pool is made from aluminum panels. They will be replacing about 5 panels with steel and the contractor said they need to be grounded. Now I have checked the rest of the panels and there is no evidence of any grounding that I can see. The only thing I have found is at the end of the pool they will be repairing there was some wire connected to the top railing and buried into the dirt.
I have worked with electrical contractors when I was younger and do electrical work at the power plant I work at. How would I ground these walls and what materials do I need.
When hanging a sconce can I connect the two ground wires together (fixture and wall)
or do I need to connect them both to the green mounted screw on back of the light fixture?
I have a grounding question. I am installing 400a service to my new home. We ran 350MCM wire underground thru 3" conduit from the 2ndary terminal (moped) to the house into a 320A Cooper B-Line meter. From the meter we ran 2 sets of 4/0-4/0-2/0 thru the wall to 2-200a breaker panels ("standard practice", according to my electrical supplier). The ground wire (#4Cu bare) from the grounding rods comes up from the ground and we're curious if there has to be a special splice connecting the ground wire to each breaker panel or can we run thru one breaker panel to then next, say by connecting the ground wire to a ground bus on one panel and running that thru to the next with #4Cu bare or #6Cu in conductor. Different electricians are suggesting different methods and the electrical inspector is unsure, but seems to be leaning towards the "special splice". Any feedback would be appreciated.
In a large bunkhouse we need to add a second range, water heater, and kitchen outlets. The existing panel is 125 AMP (with breaker), and don't want to redo entire panel. A consultant said to install a 200 AMP drop, with a panel to handle the additional load. Would you then feed each of the panels from that drop as main panels, or use a new 200 AMP panel as the main, and the 125 as a sub-panel from that? I assume in either instance, the grounding would be done as a 200 AMP service. Just realized if each was a main panel, the new one couldn't exceed 75 Amps, or total would be over 200. Any other ideas appreciated.
I am considering adding solar panels to my home to generate electricity. I will not add batteries however (to expensive) so when the grid goes down I won't get energy from the panels (you need a special inverter and batteries) so I want to add a portable gas generator for those, hopefully, limited cases.
I just wondered how the solar wiring gets interfaced into my system (breaker panel?) and can I later add a transfer switch or interlock switch when I add the generator? Or should I do that at the same time (perhaps the interface is complicated)? Thoughts? Thx
Had a Home Inspection (don't have the report yet.) The house was built in 1983. One thing the inspector said was a grounding wire should be put in from the panel in the garage to the outside box.
He also said I should have a new panel put in ($ 1,500-1,700). That's a lot of money especially when you're just buying a house. It sort of concerns me, but he didn't sound like it was urgent. I can't believe I'd have to replace circuit breakers. I'll get 3 estimates when I do this. Is this a normal problem for houses this age? I always think of my dad's 60 yr old house and he never once had a repairman. I think his electrical was ancient.
My existing service entrance consists of an external Meter can mounted on the outside of the garage wall directly behind a SD Main Breaker Panel (MBP) with a 150 amp main breaker. In order to support upgrades, I am installing a second MBP (200 amp) inside the garage in the wall cavity right next to the existing panel.
Local code requires that the upgraded Meter can be purchased from the City Utility. I have already confirmed with the local inspector that either 4/0 Al or 2/0 Cu SE cable are acceptable for both the existing and new MBP. My question is what is the code requirement for getting the 3 SE cables run from the dual lugs to the new panel? Can those conductors run into the same wall cavity where the existing panel is installed? If so, I'm certain they can't go through the same conduit nipple that connects the back of the meter can to the existing MBP. Can they route in behind/above/below the existing panel and through a hole in the wall stud to gain access to the adjacent stud bay to get to the new panel? If not, do they need to be routed out of the meter can on the external wall in conduit over to the next stud bay and then enter the wall there to gain access to the new panel? If external conduit is required I would expect it must be metallic as opposed to PVC. Best Regards, Ted
QUESTION: can I run (2) 14-2 romex wires in (1) 3/4 BX Armored cable?
SETUP: I am finishing my basement and a few main floor circuits are intermingled with the basement lights and outlets. In finishing the basement, all basement electrical will be on its own circuit. Therefore, I need to rewire some main floor items. For instance, the main floor living room outlets go through the den area below in the basement. The 3/4 BX cable goes through the ceiling to the outlets. PLAN: I plan to cut the armored cable shortly after it comes out of the ceiling (main floor floor) and just connect the first floor outlets in a series using the proper bushing and BX cable ends. I will strap the BX cable ends down and the romex as soon as it comes out. The electrical inspector already gave me thumbs up on doing this for the electric oven and cooktop (bigger wires of course). I searched and couldn't find anything to this specific question. Any input? B
I am installing a square D 100 amp panel in a mobel home and had a question. The panel came with no seperate grounding bar only 2 connected neutrel bars and the typical hot bars. I was curious as to why some panels have seperate grounding bars (for bare copper) attached to them an some do not. Thier was a green bonding screw that said if bonding the box was necessary to screw it in the nuetrel bar and attach a wire from it to the panel box. Would it be better to attach a grounding bar directly to the panel and run a wire from it to a rod in the ground?
I have a 15 amp circuit feeding a bathroom and I want to upgrade it to a 20. Can this be done without opening up the sheet rock walls and space between the first story ceiling and second story flooring?
It was wired, when it was code in the early 90's, with #14. I am thinking that I could go from station to station and connect the end of the new 12 to the end of the old 14, and then pull it through BUT PERHAPS FOR STAPLING, assuming the cable is stapled every foot and a half. If it is, and the run isn't too long, is it often possible to just tug on the cable to loosen the staples? Assuming that can be done, do I have to open up the walls and ceiling to staple the new #12 cable to the framing. I am trying hard to avoid opening the drywall. The newer paint in this particular room is impossible to match and I would have to repaint the entire room should I have to cut the wall. |