I built a free standing garage with main power tapped from the home breaker box.  The contractor pulled 4 wires via a conduit to the freestanding garage panel which supplies lights, a garage door, and two 20 amp outlets.



Everything worked well initially, but about 1 week ago one section of the lights in the building went out.  The contractor came out and found that one of the two hot wires in the garage panel was only seeing 100 volts and that went down if anything else was turned on.  He swapped one of the ground wires for the bad hot wire and everything now works. 



What would cause a situation like this where the hot wire apparently had a voltage loss?  Is it safe to continue with the fix where the faulty wire is now the ground?



Thanks in advance!
      


Similar Tutorials

How to Lay Sod - The Right Way!
   - Make sure the green side faces up! And, there are a few more steps if you want to ensure a nice looking lawn. Prepa ...
The Difference Between Volts, Amps, and Watts
   - This article explains the difference between Volts, Amps, and Watts in an easy-to-understand non-scientific way. T ...
Water is Leaking from the Toilet – What do I do? (How to replace the wax seal for a toilet.)
   - If there is water leaking from the toilet, you need to make sure that you know from where the water is leaking. Che ...


Similar Topics From Forums

I'm having quite the time finding an electrician who will quote this.  Just about all of them say that what I need is to upgrade my main panel but I want to install a new main panel that is a part of the meter base outside and make my current 100A panel a sub.   Maybe you people can tell me why nobody seems to want to do this.  Here are a few shots of the existing meter (note what is apparently a 60A base here)






and a shot of the conduit headed underground.  Like most homes built during this era, the conduit makes a right turn underground to enter through the cinderblock, ending up coming into the back of the main panel.  This conduit encloses a 4 wire feed. edit: no, actually it is only a 3 wire feed which is a problem if I want to convert the original main panel a sub.






Here's the existing panel.  It's a 60's era Square-D split panel with a 30 amp sub panel for the finished basement.  Those are low voltage wires to circuit taps for my home energy monitoring system btw.






The reason I don't want to upgrade this panel are as follows:

We won't be expanding the electrical west of this panel any more.  All planned expansion (240v car charger in Garage, planned 3 season room with grid tie Solar on the roof) will be to the east.


Upgrading the panel will require major surgery to the walls.  Due to the way the original basement is engineered there, the walls have an intricate stud pattern behind the existing panel.  I'd pretty much have to rip out a 4' section and redo it to make the access large enough to handle a 200A panel.


Adding additional circuits to an upgraded panel will require an act of God due to the finished basement construction.  There are no raceways for additional circuits.






Based on this, my thoughts were to create a new 200A main panel outside based on something like the GE model TSM420CSCUP loadcenter.  Here's a shot of this panel:






This particular panel has room for three 2-pole breakers in addition to the 200A mains.  I'd add a 100A 2-pole breaker for the existing panel, with the other two reserved for the garage/solar expansions.



The issue with the contractors who have quoted the job appears to be the conduit going to the existing panel.  I'm not sure what's wrong with it but it is apparently not compliant with current code.  Obviously the bonding needs to change, new grounding electrodes need to be driven, and a water pipe ground needs to be established to the new main panel, but what else is required?



I'd like to throughly research all the code considerations here so I can approach a contractor from a more knowledgable perspective then determine the best way to perform this upgrade.  Due to POCO coordination and the need to cut household power for the duration of the job, I have no desire to DIY this one...



So what exactly is wrong with the conduit running from the existing meter base to the existing load center?  Why is everybody telling me that I can't do essentially what I've described above?  What are the relevant code sections that will apply to this job?  Should I be chatting with my AHJ about local considerations now or should I wait until I have the code requirements down pat (assuming the latter here)?
      
Garage running Underground feeder 4/4/4 AL from main panel off dual 80 amp breaker.

Yesterday I found half the garage panel was inoperative.

Tested lugs, one of the feeders is 120V, the other is at 80-90V.

Swapped the feeders at the 80 amp main to ensure it wasn't the breaker. Same results.

Tested at the 80 amp breaker at main panel, both legs 120V.

When I remove the 80-90V feeder off the 80 amp main panel breaker and test it at the garage it drops from 80-90 to 0.



No breakers trip. Is this one feeder line broken underground or split open and grounded to earth?
      
Hi,



I would like to wire a switch to be able to cut the power to the ceiling mounted outlets that feed our garage door openers. Running new wiring to them will be a bit cumbersome, so I am hoping to avoid that. The ceiling outlets are powered by light fixtures in the garage (one near by each outlet). There is a 3 wire romex cable running from the light switch to the first light and another one between the lights, and then regular 2 wire romex cables from the light fixtures to the outlets. The red wires in the 3 wire cables to the lights are switchable, the black wires are always hot.



I mainly want to be able to cut the power to the doors when we are away on vacation, and the reason for that is that one night both doors somehow opened up - I have no idea why. I'd hate for that to happen when we're away. Unplugging and plugging in the openers is a bit of a hassle due to the high ceiling.



I thought about wiring in a switched outlet so that I could just reach up with a long handle of some sort and switch off the power to the outlet. It would not be ideal, but definitely easier than getting the ladder out and unplugging the door openers.  However, there is possibly another option that I'd like some input on if anyone cares to comment. I believe I could wire in a switch on the wall next to the light switch that would allow me to cut the power to the black wires in the 3 wire cables. This would cut the power to the ceiling outlets and anything downstream from there (possibly an outside light, I would need to check on that).



My question is, are there any potential issues with this sort of wiring? Is there perhaps any code violation if both hot wires in a 3 wire cable can be switched off separately?



Thoughts?
      
I just ordered some Arlington Siding Mount Kits with built in electrical boxes to install some lights on the outside of my garage. 



So, the issue is, the mount kits' built in electrical boxes are only 6.8 cu each and I'm wiring the lights up with two 3-way switches.  The source is at the first switch, then on to the two lights and then to the second switch.  There is not enough room to do the splices and connection in the built in boxes (I'm using 12awg, but even if used 14 still not enough room), so my plan was to wire everything to a central junction box inside the garage between the two lights and make the appropriate connections there. 



I'm attaching my rough sketch of the planned connections (omitting ground wires).  Can you guys please confirm this is correct?    Thanks for the help!



To clarify the drawing, blue is white (neutral) and the blue with black tape coming off second switch is marked as hot.  (I'll also mark it as hot in the J-box).  Yellow Triangles are wire-nuts.
      
Hi everyone, this is my first post.  Hope it works out!



I have a new detached two car garage with two 115v 15A circuits in it.  I want to put in a 12000 BTU window air conditioner.  One circuit runs 10 fluoresent bulbs in the garage and a few in the house but also runs a few outlets in the house that see occasional use by a 12A vacuum cleaner.  The other is solely used for the door opener and outlets in the garage where I often use a 12 amp skill saw. 



Both circuits are aqccessible, which one should I choose?



Puttster
      
I am having a garage/shop built on my back lot.  The PoCo will place a meter pan with a disconnect switch (not an OCPD) on a utility pole that is already in place and about 40 feet from the garage.

What will I need for temporary construction power?  I know I need GFI receptacles and OCPD but what about the ground?  Will I have to drive a rod?
      
I want to put switch in house to control lights in garage.  How do i run romex from garage through drywall into house?  Do i need to use conduit to secure wire.  Thanks
      
I want to set up a hobby woodworking shop in my garage. I was going to run from the panel maybe four or five 12/2's to accommodate lighting, power tools, dust collection, etc. or should I put a subpanel 60 to 100 amp? The main panel is on an outside wall on one side of the house and the garage is on the opposite side of the house. The distance from the panel to the entry into the garage is about 50 ft. I would be pulling wire- a straight run- through a ceiling chase that runs the length of the house. No basement.
      
Hi All -



I'm looking to add some outlets in the garage (currently have only one) for my workshop. At most, I'll be using a 13 amp table saw and 11 amp shop vac simultaneously.



I had an electrician come out for an estimate and while it was a fair price, I want to do this myself to build some confidence.



A few questions: he said they would probably add 2 15 amp circuits to handle the load. Is that necessary? Or can I add say one 30 amp circuit?



2nd: my garage is drywalled (and insulated). It will be much easier to have the outlets (and wire) on the exterior of the wall. What would be the best materials for this? My breaker is located in the garage and the outlets would run directly out from the side as seen in my poor illustration.



Since it is set into the wall, I'll have to run the wire from the breaker into the back of the first box. Is that as simple as it sounds, or is there something that I am missing?



Any help is appreciated.



Cameron
      
hi i need a power supply to my garage/workshop, i have a spare in my consumer unit in my house type b 32a mcb, and will i need a 4mil swa?? or 6mil swa?? from the cu in the house to the garage cu,(63A. 30MA. RCD., 1 x 6A lights + 1 X 16A scokets. MCB),, i will be useing a welder, grinders with a(240v- 110v transformer) and there will be 2 double scoket outlets in the workshop,,,is this all correct?? thanks,